79. Rehabilitation of R14 Bălți – Sărăteni Road (Rehabilitation of R6 Chisinau-Orhei-Balti Road)

Lot 1: Contract RSP/W11/01: Rehabilitation of R14 Bălți – Sărăteni Road, km 26+600 – km 38+300 (Rehabilitation of R6 Chisinau-Orhei-Balti Road, km 99+530 – km 111+230)
Lot 2: Contract RSP/W11/02: Rehabilitation of R14 Bălți – Sărăteni Road, km 43+000 – km 61+000 and bridge at km 64+756 (Rehabilitation of R6 Chisinau-Orhei-Balti Road, km 76+700 – km 94+700 and bridge at km 72+944)

Current status: Contract Awarded

78. Supervision of Rehabilitation Works under the Contracts:

Lot 1: RSP/W11/01: Rehabilitation of R14 Balti – Sarateni Road, km 26+600 – km 38+300 (Rehabilitation of R6 Chisinau-Orhei-Balti Road km 99+530 – km 111+230)
Lot 2: RSP/W11/02: Rehabilitation of R14 Balti – Sarateni Road, km 43+000 – km 61+000 and bridge at km 64+756 (Rehabilitation of R6 Chisinau-Orhei-Balti Road km 76+700 – km 94+700 and bridge at km 72+944)

Current status: Contract Awarded

74. Local Roads Improvement Project: 

Improvement Works on  Section 1: Corridor 13,  Section 2: Corridor 8.3 and Section 3: Corridor 11, under the Contract LRIP/W1/02

Section 1: Corridor 13, L 390 Pirlita-Nisporeni road, km 0+000 – km 33+50 L 431 Păruceni – Seliște – Vînători Road, km 0+000- km 4+200 R25 Road – Seliște village, km 0+000 – km 3+600
Section 2: Corridor 8.3, L405 Road from R21 – Oniscani, km 0+000 to km 9+960  
Section 3: Corridor 11, L313 M2 – access road to Miclesti village, km 0+000 to km 5+000 L314 M2 - Peresecina - Hîrtopul Mare – Ohrincea road, km 1+640 - km 15+390 L314 M2 - Peresecina - Hîrtopul Mare – Ohrincea road, km 19+810 - km 24+300 L314 Izbiste village Bypass, km 15+390 to km 19+810 

Current status: Cancellation of Bid